Since I am attempting to keep track of the actual current and future cost of wind generation projects as opposed to the fairy tales that Wind advocates
are telling, here is a tidbits of information from Cleantech:
"Thanet Offshore Wind project off Margate, Kent. . . . Vattenfall to build the 300-megawatt wind farm, estimated to have a construction cost of £780 million." (That is a little over $1.5 billion, a little more than $5000 per kW.)
Thursday, November 13, 2008
Subscribe to:
Post Comments (Atom)
Followers
Blog Archive
Contributors
Some neat videos
Nuclear Advocacy Webring Ring Owner: Nuclear is Our Future Site: Nuclear is Our Future |
||||
Get Your Free Web Ring by Bravenet.com |
links The Weinberg Foundation
- The Weinberg Foundation
- Deregulate the Atom
- LFTRS to Power the Planet
- Sustainable Energy Today
- ANS Nuclear Cafe
- Thorium Power
- The Nuclear Alternative
- Yes Vermont Yankee
- Nuclear Townhall
- NNadir's underground blog
- oz-energy-analysis.org
- Environmentalists For Nuclear Energy
- Save The Climate (Sauvons Le Climat0
- The Energy Tribune
- masterresources.org
- Nuclear Fissionary
- Nuclear Archer
- This week in batteries (TWIB)
- Gerald E. Marsh & George S. Stanford on Nuclear Policy
- The Capacity Factor
- Canadian Energy Crisis
- Institute for Energy Research
- Energy from Thorium Documents
- Energy from Thorium Discussion Forum
- Next Big Future
- RadiationAnswers.org
- Knowledge Problems
- Brave New Climate
- Thorium electronuclear
- AREVA Blog
- The Energy Collective
- Climate Change Politics
- Reactor Physics Group Publications
- Alexander DeVolpi on nuclear-weapons nonproliferation
- ECOWorld
- New Papyrus Magazine
- Pronuclear Democrats
- American Energy Independence
- coal2nuclear
- Energy Density
- SUSTAINABLE ENERGY - WITHOUT THE HOT AIR
- The Atomic Show
- Atomic Watch
- Pebble Bed Reactors
- The Thorium fuel cycle
- Simon Nisan on Nuclear Desalination
- Dr. Ralph Moir
- National Wind Watch
- Wind Energy Resource Atlas
- solar calculator
- THE NUCLEAR ENERGY OPTION by Bernard L. Cohen
- Oil Drum
- Solar Buzz
- Clean Brake (Tyler Hamilton)
- GM-Volt
- Fuel Cycle Week
- Depleted Cranium: Dr. Buzzo's Bad Science Blog
- Blogging About the Unthinkable
- Uranium Information
- Frank Munger
- The Information Bridge
- Alvin Weinberg Papers
- Left-Atomics (David Walters)
- bartoncii
- Real CLimate
- 1 nuclear place
- World Nuclear News
- David Walters
- NNadir
- NIE Nuclear Notes
- nuclearstreet
- Idaho Samizdat
- Atomic Insights blog
- Energy from Thorium
- A Musing Environment
1 comment:
If it matches the 36% capacity factor of the UK's first offshore wind farm(North Hoyle) those $5 000/kW are equivalent to $12 500/kW at 90% capacity factor(as commonly achieved by nuclear plants).
If pumped hydro storage is used to meet most of the intermittency and produce baseload power(instead of dirty coal and gas) it would not add terribly to the amount of electricity that needs to be generated. The worst case is that 64% of electricity from the plant needs to be stored(worst case is that the plant is fully on 36% of the time and fully off for the rest); with 80% round trip efficiency for pumped hydro storage that comes out to a worst case average efficiency of 87% for baseload.
The pumped hydro storage is going to be rather costly however. I only have really old numbers, I fear they'd be rather more expensive today; but I'm going to do a quick and dirty estimate of the cost. If the dinorwig generating station is representative you get 8.6 GWh of pumped storage(1.7 GW peak capacity) for £(1974)450 million. Assuming 3% per year inflation and then converting from £(2008) to US$(2008) at the current exchange rate gives $1.8 billion. Assuming you can get by with 24 hour backup most days out of the year you need 24 kWh of backup per kW of offshore wind, that comes to $5000/kW for back-up. If I'm not mistaken cement and steel have gone up a lot more than general inflation in recent years so that may well be rather a lot optimistic.
If you add in various costs for backup(you have a fair chance that wind will die down for a solid week in the middle of winter when power consumption is highest, this will probably be met with natural gas) and possibly transmission(your link made no allusion to whether or not it was included in the cost estimate) and cost of finance(again, link doesn't say whether paying interest on loans is considered), it wouldn't at all surprise me if the final tab was in the $20 000/$30 000/kW for providing baseload generation.
Post a Comment