Energy from Thorium's Recent LFTR Cost Thread

A recent Energy fromThorium discussion has once again brought to the fore questions about MSR/LFTR costs. "Zeropoint" kicked off the discussion:
I’m a LFTR n00b so forgive me if this topic has been addressed many times. Also please point me to any threads that already talk about this. I did a search for the other threads but I didn’t see the information I wanted.
I am trying to understand the economics of LFTR.
I am taking my data from the OECD/IEA “Projected Costs of Generating Electricity” report 2010 edition.
Using that data I wanted to know estimate LFTR overnight costs (not taking into account the time value of money) and operating costs.
For the current costs of nuclear, coal and gas plants I went to tables 3.7a, 3.7b, 3.7c in the report. I dropped the two highest and lowest plants as well as any others that looked out of place. I then use the extremely scientific method of averaging them. My results are in the attachment below.
(I cannot reproduce Zeropoint's attachment. Readers will jave to look at the original comment.)
Overnight Costs of LFTR
I figure the theoretical lowest cost for LFTR is the overnight cost of a gas plant since LFTR could be interpreted as a nuclear heat powered gas turbine. Since coal and nuclear have a less efficient conversion efficiency and higher capital costs due to the steam cycle, I am going to make another scientific assumption and assume that the difference between the costs for Coal and Gas is due to the capital cost of the water condenser system, the more efficient conversion, and the efficiency of having the gas turbine factory made which you drop in place. That is a different of $1475. The cost going from the coal plant to the nuclear plant is then the cost of the containment, the nuclear reactor and the redundant systems. That is a difference of $1875. Assuming that the containment is only a third of the 1875, it means that LFTR could be built for
LFTR_Overnight_Cost = 1028 + 1875 * 2/3 = 2258 USD/kWe
I am surprised it is so close the cost of a coal plant. I thought it would be a little higher.
Fuel Cycle
I am going to assume 0.1
Operation & Maintenance
You may be able to have less operators at a LFTR plant than a traditional nuclear plant but the maintenance costs will be higher due to the replacement of the graphite core. I am going to assume that O&M is the same as traditional nuclear, 13.6 MWh.
Construction Time
If LFTR components are factory made and then plumbed up on site then you can probably get the same construction time as a coal plant. Not sure how long the regulatory piece takes. Assume 4-5 years with one of those years being regulatory.
Plant Lifetime
This I have no clue on this. Any guesses?
Decommissioning Costs
Will probably be the same as traditional nuclear at 15%.
Any thoughts?
At this point I would note that Nuclear Green makes a number of assumptions that differ from those offered by "zeropoint". Nuclear Green substitute assumptions are intended too lower MSRs/LFTRs costs, to decrease MSRs/LFTRs construction time, and to increase the speed and number of MSRs/LFTRs deployed before 2050. Thus from the viewpoint of Nuclear Green, Zeropoint makes very conservative assumptions.

"Lars" responded to "Zeropoint,"
It is tough to get a good cost on current nuclear power plants - just look at the variance in actual costs to build existing reactors. The estimates have generally been even to 30% cheaper than LWRs but the estimates are very old.
If LFTR takes off like I think it should then there will be a substantial learning curve advantage to factor in - especially in the all critical time to build.

Here are the reasons we think it should cost significantly less.

Compared to the old LWRs new ones have increased in price dramatically due in large part to redundant engineered safety systems and schedule delaying tactics by opposition intended to drive up the cost. LFTR has its safety due to physics so it is reasonable to hope that the cost will not go up.

There is no high pressure system in LFTR so we don't need the super thick, 600 ton pressure vessel that can only be made in Japan today. In fact, there is reason to think that most of LFTR could be factory assembled and shipped by barge, or truck to the site reducing construction time (similar things are being done for future LWRs too).

Dry or Wet/Dry cooling could allow placing the reactors away from rivers/lakes/oceans generating less opposition and less unique environmental impact reports.

Counter to these nice things is that the reactor is fundamentally different and regulators won't know what to do with it. These days they tend to over-regulate. Some things that were allowed and have been grandfathered in for LWRs likely won't be tolerated for LFTRs.

But - the majority of LFTRs won't be installed in the US or EU so our over-regulation will matter less.

For plant life-time, I'd guess this doesn't matter too much but the general target for modern power plants is 60 years.
Lindsey commented,
(My) gut feel says 2,000 - 3,000/kW for a 400 MW+ sized plant, but my capital cost estimates say for a simple graphite free tank type core $1,350/kWe all in, and that sounds too cheap to me.
Lindsey's too cheap comment is all too familiar to be. Three years ago, I attempted to estimate LFTR costs, using the small factory manufactured LFTR mode; and a number of different assumptions, and kept getting estimates that struck me as far too low.

Lindsey also offered construction time estimates that were far more conservative than those which I believe are both desirable and obtainable.
For standardized designs the equipment manufacture if made to order would be about 10 -18 months depending on hardware used, on-site construction time could be 12 - 18 months, followed by 6 - 12 months commissioning and testing, so all of that together get's you out to 4 years approx from financial investment decision (FID)
Lindsey is thinking in terms of traditional reactor construction methods, but I have reason to believe that research aimed that drastically shortening small reactor field set up times may be underway.

"Ida-Russkie" commented,
The NRC hearing process for the AREVA eagle rock plant is set to last two years by law. Is a reactor going to be easier to get approval? So, this is one area where there should be some relief after you prove one can be built. the hearing process is to stop the design changes which bankrupted some nuclear plant builds in the past. The environmental impact study took one year to submit.
"Ida-Russkie's" comment clearly assumes a businesses as usual operation for the NRC, however, the potential inherent safety of MSRs may lead to big changes in the regulatory process, and the recycling of coal fired steam plant locations, may drastically change the state permit situation, since permits have already been issued for coal fired power plant sites.

"Cyril R" pointed out one of the reasons for low MSR costs,
different reactor builders are using different numbers of loops. Westinghouse seems to prefer a few big loops for the AP1000. Areva likes to use one more loop. 4 for the EPR, this is 1600/4= 400 MWe per loop compared to 550 MWe for the AP1000. It seems plausible that the loops should be as big as possible for economics. But the LFTR has a remote maintenance requirement. Multiple smaller loops could allow easy modular replacement. The LFTR has less pumping power than a PWR. On the order of 7-8x less I believe, based on the AHTR pumping power requirement of 1.46 kW/MWth and 8 kW/MWth for the EPR, combined with better turbine efficiency, gives around 7-8x less pumping power per kWe. It could be even smaller than that, as the temp drop is larger for LFTR, and this likely more than compensates the heavier fuel salt pumping requirement.
Pumps are important and usually expensive components of reactor design. The EfT discussion makes clear that Westinghouse has chosen to lowe its pump costs by decreasing their number, with each of 2 pumps moving half of the AP-1000 reactor coolant.

"Zeropoint" calls attention to the cost of regulation,
Sorry to dwell on the subject of the NRC which I know all of you love. I wanted to understand the approval process a little better since I didn't have it in my cost estimates.

I just listened to Atomic Rod's podcast #154 "Atomic Round-up With Five Experts" where he mentions that for new nuclear plant designs you have to pay the NRC $200+ an hour for them to analyze and authorize new designs.
Wow! That is going to be a drain on any startup especially for a LFTR based design where the NRC has to be educated on the technology. Is this still the case (the podcast was done a year ago)?

At $250 an hour, one man year costs $500,000 ($250*40hrs*50weeks/yr). Does anyone know how large an NRC team would be to analyze new designs? If the team was 10 people for 10 years, then that is $50mm to get a design approved. That is a pretty good size chunk of change.
Lars estimates that the cost of NRC regulatory approval runs about $50,000,000. With the Cost of LFTR design runint to $500,000,000. Of course in Energy circles $500,000,000 does not amount to a lot. Solyndra, a Solar PV systems manufacturer, has just filed for Chapter 11 bankruptcy. Solyndra received over $500,000,000 in Federal loan guarantees in 2009 in addition to nearly One Billion Bucks from venture capital firms. Well, the chumps who just parted with one and a half billion bucks were warned. Warned by Nuclear Green, and Brave New Climate.

Cyril R, comments
The purpose of the NRC is to maintain the status quo on nuclear. Molten fuel reactors could potentially break the status quo, so the NRC won't license it in our lifetimes. However, they will gladly take all your money to research it to death, and laugh all the way to the bank.

Its like, asking the king to help start a revolution for democracy.

http://ergosphere.blogspot.com/2011/07/quote-without-comment.html

MSRs have the real potential to work, and work much better than LWRs, so the NRC won't help you.
Cyril's link points to a quote from Ugo Bardi
Bureaucracy is a tool to keep the world as it is, not to change it. So, in perfect Tainter-style, the system works hard to avoid innovation, not to promote it. It is almost impossible to be financed to study resource depletion; that would highlight problems that would require changes and that's a no-no. Instead, it is still possible to obtain research grants as long as there is no risk that the results will threaten the status quo. Hydrogen as a fuel is a good example. It is high-tech, fashionable, sophisticated, popular, environmentally friendly, and it doesn't work. This last characteristic makes sure that its development will bring no changes whatsoever.
Several issues touched on in the LFTR cost thread invite Nuclear Green posts, but one by Chemical Engineer Kim L Johnson is down right pregnant. Johnson writes,
I'm a chemical engineer who has been working to develop industrial Fluorides for many years and have assembled lots of online documentation for the benefit of Lftr and the like.

If you have any significant interest in Fluorides, structural materials for Fs and in which forms of whatever elements are best for the Lftr bath & containment, I would be happy to send you lots of link.

Sadly however, I can no longer post important details Freely. Serious Foreign competition could very well, in a few years' time, leave the US so far behind in our own Fluoride-Energy tech we'd never recover economically.
Fortunately, the very successful efforts of TEA & other "T Com" leaders -- fruit we shall soon see in the Senate & elsewhere -- should shortly enable guys like you, (hopefully) Lars, and many others to develop Thorium-enabled technologies full time (*just* getting off the phone with this effort's champion) !
MSR/LFTR endeavors are being launched. Some are so clouded in secrecy that their very existence may be unknown to me at this point. Lots of things are going on that I can only guess at. Part of this secrecy is due to the entry of the Chinese into the MSR/LFTR field, and part is due to proprietary concerns.

The EfT discussion suggested that the Nuclear Green view that MSR/LFTR technology can lower nuclear costs, is shared by engineers and scientists who are aware of that technology. It also suggests that other members of the EfT community may be more wed to business as usual assumption than Nuclear Green is. However, the discussion points to concerns about Federal regulation as an barrier to technological advancement that require further attention.

The EfT LFTR cost thread makes conservative assumptions, but still suggest that LFTR costs may be so low that at least one discussion used the words too low to make sure we knew he is sane. At the very least, it can be concluded from the EfT discussion that MSR and LFTR technologies may be a road to lowering the cost of nuclear power.

Monday, December 28, 2009

Updating ORNL MSR Design and Cost Studies

In order to understand the importance of the LFTR, we must return to the original research reports and other working documents prepared at Oak Ridge National Laboratory between 1950 when ORNL research on the Molten Salt Reactor concept began at ORNL and 1980 when ORNL scientists who had MSR expertize, wrote their last proposal. ORNL researchers in the 1960's and 1970's argued that MSR development would not cost a lot and commercial MSR was cost competitive with then current LWE designs. Since the 1970's some of the development problems for the MSR have been independently solved. Much of the most challenging MSR technology is also used in other high temperature reactors, and in fusion reactors. So ongoing research and development on these technologies has contributed to the development of the technology proposed for the MSR. At the same time proposed design of the Thorium Breeding Molten Salt Reactor (the LFTR), has increasingly diverged from current Light Water Reactor (LWR) designs. Canadian physicist David LeBlanc has proposed a radically simplified of the already simple MSR/LFTR core design. LeBlanc's redesigned core could be assembled in less than a day, in a LFTR factory. LeBlanc also suggests the use of
less expensive iron alloys including the common stainless steels 304 and 316 [which] have also shown promise at somewhat lower operating temperatures.
The use of multiple cost saving strategies also holds promise for lower LFTR costs. These would include the factory construction of small LFTRs, which would be transported by truck, rail or barge to the power plant location, the recycling of old coal fired electrical generation facilities as LFTR locations. The use of underground housing, rather than massive containment structures. The manufacture of large numbers of reactors on a factory assembly line will increase the speed of progression on the manufacturing learning curve, leading to even lower prices.

During the last 40 years the cost of light water reactors has risen dramatically. Rigorous NRC certification standards have dramatically increased the cost of parts design. Nuclear critics point to $50,000 being spent to design as $5 nuclear part. Mass production means that each part can be used on hundreds and even thousands of reactors, lowering nuclear costs. Recent developments in LWR design point to reactor simplification as an important step for lowering nuclear costs. There is little doubt that adopting LFTR would dramatically simplify nuclear designs.

In the absence of a serious design effort by a contemporary nuclear design team, it is difficult to estimate exactly how much LFTRs would cost. ORNL MSBR design studies, although old, do hold clues to nuclear costs. ORNL-TM-1851 (SUMMARY OF THE OBJECTIVES, THE DESIGN, AND A PROGRAM OF DEVELOPMENT OF MOLTEN-SALT BREEDER REACTORS) is a good starting point for looking at LFTR cost estimates. TM-1851 estimated that a LFTR type MSBR could be developed in 8 years at a cost of 125,000,000 1967 dollars.

This estimate was made before ORNL researchers had their three experience of with the Molten Salt Reactor Experiment (MSRE). The MSRE pointed to some real but hardly insurmountable technological problems to be overcome before a LFTR type MSBR could be commercially viable. Thus later ORNL design studies, and R & D plans were more realistic about development costs and time frames.

The early ORNL MSBR designs were fairly complex. TN-1851 developed its cost estimates from analogies to the costs of the light water reactors of the time. But in fact later developments in both technologies diverged.

Recent thinking about LFTR design has moved on the 1960's and 1970's designs, and more recent actually point to lower, and potentially much lower LFTR costs, than could be obtained by simply replicating old ORNL designs. Thus it is quite possible that old ORNL estimates for MSBR costs, when adjusted for inflation could be actually higher than future LFTR costs. TM-1851 estimated that power could be generated by MSBRs for as little as 2.6 mills per kWh, of about 1.7 cents per kWh, inflation adjusted 2009 costs. This would be most encouraging, if we could rely on this figure.

In another post, I pointed to yet other ORNL studies which also point to similar conclusions about LFTE costs. Finally I point in the same post to the development and manufacturing costs for the Airbus 380 aircraft. Airbus invested €11 billion plus that in the development of the A380. At a cost of $327 million the A380 would be if anything more complex and more expensive than the modular LFTR. Thus we have a reasonable hope that LFTR costs would come in at under $2 per watt of generation capacity, and $1 per watt or even less is not beyond the realm of possibility. We need more research to get a better understanding of LFTR cost estimate, but my preliminary studies suggest that the LFTR could represent a dramatic breakthrough in lowering the cost of post carbon energy.

Tuesday, November 24, 2009

Indian Nuclear Plans

The World Nuclear Association has published a long new account of the advances in the Indian nuclear program. Things are now moving very fast and three dozen reactors reactors are either planned or under serious consideration. Indian plans include light water reactors from Russia, France, and the United States, in addition to a locally designed Light Water Reactor.

Why the plunge into foreign Light Water Reactors, after India has painstakingly developed its heavy water reactor technology? The reason becomes obvious when we learn that the Indians are now expanding their fast breeder reactor plans. The WNA tells us
Longer term, the AEC envisages its fast reactor program being 30 to 40 times bigger than the PHWR program . . . this will be linked with up to 40,000 MWe of light water reactor capacity, the used fuel feeding ten times that fast breeder capacity, thus "deriving much larger benefit out of the external acquisition in terms of light water reactors and their associated fuel". This 40 GWe of imported LWR multiplied to 400 GWe via FBR would complement 200-250 GWe based on the indigenous program of PHWR-FBR-AHWR. Thus AEC is "talking about 500 to 600 GWe nuclear over the next 50 years or so" in India, plus export opportunities.
Oh wow, talk about ambitious! As i keep saying the Indians intend eat every ones lunch by running their industries on low cost thorium power. Even though foreign reactors are more expensive than Indian designed reactors, they fit into Indian plans, because they produce lots "spent fuel". In other countries "spent fuel" is considered a problem, and is called nuclear waste. In India spent light water reactor fuel is fuel for fast breeder reactors. And fast breeders will produce both electricity and the start up fuel for Advanced Heavy Water Reactors. The AHWRs will be breeders too, so as long as India has thorium, it will have nuclear fuel.

Unlike China, India does not have a legacy of coal, and further unlike China, India is not cursed with a large domestic coal supply. The Indians have known for 60 years that the key to their energy future would lie with nuclear power, and have doggedly pursued a nuclear development program. Along the way the Indians were able to develop really low cost but good quality reactors. Locally designed and built Indian reactors cost 40% less than Chinese reactors. And needless to say both cost a whole lot less than American and European reactors. The Indian reactor price advantage could begin to tell in 20 years when India and China start their post carbon energy program in ernest.

Current Chinese plans for post-carbon energy call for an everything but the kitchen sink approach. And even the lowest carbon Chinese energy plan calls for over 40% of Chinese electricity to be generated by fossil fuels in 2050. The Chinese expect to be building 4th Generation reactors by 2050, but it is far from clear what role they will play in Chinese nuclear plans.

The Indians clearly have charted a route to a high energy, low cost nuclear future. The Chinese as of yet have not. Of course Indian plans, though good, could be even better. The Indians are committed to do a lot of fuel reprocessing, a decision the Chinese appear to be also following. Both nations are involved with expensive approaches, and current fuel reprocessing technologies tend to loose too much plutonium, Indian reactor and fuel processing costs could be lower, provided the Indians adopted Molten Salt Reactor technology. A LFTR would include fuel reprocessing technology with each reactor unit, and would not produce plutonium. LFTRs need not produce plutonium at all. The Indians are probably years away from doing that, but a rapid program ofLFTR development in the United States could lead to lower post carbon electrical costs and would keep our industrial economy competitive with India.

Sunday, October 11, 2009

Letters to Jesse 4: A Second Manhattan Project?

Dear Jesse, The conventional view is that it would take a long time to develop Generation IV nuclear technology. This is mistaken because the Indians expect to complete a commercial Generation IV Fast Breeder Prototype Reactor in 2011, and then begin to build standard production reactors immediately after. They currently expect to complete at least 4 commercial fast breeders by 2020, and more later.

The long gestation period view assumes that the development of Generation IV technology would be conducted with business as usual approaches. But if we think that the fate of human society would rest on the pace of a Generation IV development project, would a business as usual approach make sense? Alternatives would be a simi-Manhatten project model and a mini-Manhattan project approach. The difference would have to do with time scale, with the Simi-Manhattan project approach trying to bring in everything in a two to three year time range, while the mini approach might take 5 years. The mini approach might cost $20 billion, perhaps twice the cost of the business as usual approach, but at the end of the five years a saleable product, and a factory to build it would be ready.

Let me illustrate what I mean by the Manhattan Project approach. The Mahnattan Project was a massive research, development and production project conducted during World War II. The aim of the project was the development of deliverable nuclear weapons. That goal was meet. Rather than develop one single approach to the project, and perfect it, project scientists undertook to develop parallel approaches to project goals. Scientists identified two fissionable materials that could be used in Nuclear Weapons, U-235 and Pu-239. Rather than settle on one approach, they decided to develop two weapons, each using one of the fissionable matereials. The method of producing Pu-239 was deemed very dangerous, and the production facility was located in a desert in Washington State. Production at the Washington State site was to be accomplished through the use of 3 large, experimental reactors of a type never built before. Construction of the reactors began in August 1943, The first was finished in September 1944, and the final reactor was completed by February 1945. The entire 3 reactor project was completed in 18 months. Despite questions about the safety of their design, the Hanford reactors never had a serious accident. Their designer, Eugene Wigner was trained by a chemical engineer who had done notable chemistry research in the 1930's.

A further research reactor was build in Oak Ridge with an overlapping time schedule to the Hanford Reactors. The X-10 Graphite Reactor, was intended to produce plutonium for the research required to waponize it. The designer of the Graphite Reactor was a young scientist, who had recently acquired a PhD in biophysics from the University of Chicago. Despite the fact that the youthful Alvin Weinberg had more training in biology and mathamatics than in physics, and had no engineering training at all, he was able to design a reactor that was built in 10 months, and performed flawlessly, and proved a valuable research tool.

Thus from December 1942, when Enrico Fermi's Chicago pile went critical, and November 1944, the design of reactors leaped forward by would have required a business as usual approach a generation to accomplish. Further more, the designers of these reactors would have been viewed as completely unqualified to perform this task, because they lacked the proper educational background.

In addition to the development of reactors to facilitate the production of a plutonium based nuclear weapon, the project to develop a uranium based weapon had an equally remarkable history. Three separate uranium enrichment projects were developed in Oak Ridge. The Y-12 project developed and used electro-magnets in devices called calutrons to seperate the uranium isotopes. The calutrons required a huge amount of copper wire, and when copper was in short supply, the Manhattan project borrowed 14,700 tons of another electrical conductive metal, silver, from the United States Treasury to wire the magnets. A second uranium separation process was housed at K-25, which when finished was the largest building under one roof in the world.

The K-25 project would have cost $8 billion today. While it was being built, scientists and engineers did not know if they could make the gaseous diffusion method work. Again, a huge investment produced in months what a business as usual approach would have required years to accomplish.

I would argue that given the dual crises of CO2 emissions/Anthropogenic Global Warming and Peak Oil, and the potential for Generation IV nuclear technology, a rapid nuclear development program is demanded.

If a Manhattan project type endeavor were undertaken, regulation would be expidited but safety not compromised. The NRC would work alongside reactor researchers, establishing reasonable safety standards, and passing them on. During the development period the NRC should determin that reactor developments are meeting all NRC safety goals. The complete design should already have an NRC license, even before the prototype is built.

In the Simi-Manhattan project alternative design approaches would be researched in parallel, while in the mini approach they might be investigated sequentially. Both would involve spending at a robust level. There are shortcuts to development including licensing sucessful technology. This might include licensing Russian BN-600 technology, Indian Fast Breeder Prototype Reactor technology, in addition too drawing on American Experimental Breeder Reactor-II (EBR-II) technology and experience. I am not a big fan of the LMFBR type, but it is probably inevitable that we are going to build some, and if we do, we might as well develop and build them fast.


That document assumed a business as usual approach, and suggested development plans that would take a generation to realize. How much would it cost?

According to ORNL-4812, up to 1972 ORNL had spent $130 million dollars on MSR development. In 2009 terms this was less than than one billion dollars,

In 1980 the ORNL staff estimated that a commercial DMSR could be developed for $700 million (about 2.5 billion in 2009 dollars). Given another 2.5 billion for the development of the LFTR prototype we would have a total investment of between 5 and 6 Billion 2009 dollars investment. At that point there would be a product ready to go on the assembly line. Thus the total investment in the LFTR would be comparable to the Federal investment into the LWR. It would be one fourth the investment made so far in unsuccessful American LMFBR technology.

My analysis suggests that with factory production and by recycling coal fired power plants, modular LFTRs can come online for an investment as small as a dollar a watt. Let us assume that the actual cost is twice that. We still have a price for LFTRs that is lower than the 2009 price for windmills, even with a capacity factor no better than the windmills, the LFTR would be a far better buy because of its superior flexibility.

It would be nice to imagine a private enterprice investing in the LFTR. Is it possible? $5 billion would not be unreasonable for a private business invest in LFTR development. There are American businesses that are capable of writing a$5 billion check for LFTR development today. Consider the €11 billion plus that Airbus invested in the development of the A380 aircraft. At a cost of $327 million, the A380 would be, if anything, more expensive than the modular LFTR. In fact it is doubtful that Airbus will ever recover the Airbus 380 development cost, while the LFTR potentially could be quite profitable.

Compaired to the cost of renewables, the Manhattan project approach would be an incredible bargain. For example, the German newspaper Die Zeit recently reported that the costs of photovoltaic instalations built in Germany up to 2008
will amount to even more than 30 billion Euros.
And how much electricity will German consumers get for their investment? A recent estimate reported that in 2008. German PVs produced 4,300 GWh, about half the power output of one conventional nuclear reactor. 30 billion Euros would pay the development of both Sandia's "Right Size" Reactor, a small, factory built Fast Breeder Reactor, and the the Liquid Fluoride Thorium Reactor, a very safe, factory build reactor.

Eventually, the LFTR will prove to have significant advantages over the Fast Breeder Reactors. First the core of the LFTR is smaller, hense the structure ment to house the LFTR core will be smaller, and lower cost. Secondly the LFTR has safety abvantages over the fast reactor. Even if the fast reactor proves in practice to be as safe as the LFTR, that safety is not entirely inherent, and will come at a cost. Finally, fuel reprocessing with the fast reactor, will be far more expensive than with the LFTR.

Given the very great importance of a rapid, and massive world wide deployment of low cost nuclear technology capable of safely meeting human energy needs. a Manhattan Project type approach to facilitate the development of promising nuclear technology seems more than warranted. Indeed given the potentially disastrous consequences of failing to safely meet human energy needs, the rapid development of promising technology, is an imperative, not an option. - Charles

Saturday, July 4, 2009

American Energy Independence: LFTR Deployment and a Surprising Turn

July 4, 2009
My views on global warming mitigation are relatively simple. Perhaps something like 60% of the world's energy, perhaps more, can be supplied from one source, thorium fuel cycle, Molten Salt Reactors. The recoverable amount of energy in the earth's crust in the form thorium is something like 15 times what humanity can consume before solar expansion turns the earth crust into a cinder. I have argued that Thorium fuel cycle, Molten Salt Reactors or Liquid Fluoride Thorium Reactors (LFTRs) are relatively simple machines, that can be mass produced in factories. The cost of developing the LFTR is likely to run between $5 and $10 billion. The LFTR is no more complex than an Airbus 380 that cost $13 Billion to develop and $300 Million to build. LFTR cost with interest are likely to run between $1.20 and $2.00 per Watt. LFTR's can be built from common material like stainless steel. When built from more exotic materials such as Hastelloy-N , LFTRs can perform with perhaps 15% greater efficiency, but the advantages of the greater efficiency may be outweighed by the lower cost and potential for rapid deployment of stainless steel LFTRs.

Modular LFTRs with rated generating capacity of between 100 MWe and 400 MWe can be built in large numbers, and set up quickly. Because of their small size and low cost, LFTRs will be far easier to finance than traditional large reactors. They can be built and put into service over periods of months rather than years. Large numbers of small modular LFTRs can be clustered to produce the electrical output equivalent of large nuclear plants. Small LFTRs can be located in distributive generation fashion, close to electrical consumers. Thus LFTR deployment in most cases will not require large and expensive additions to the Grid. LFTR can be air cooled, thus their operations will not be impaired by droughts and water shortages.

If LFTR deployment began in 2020, with a large LFTR factory Most US electrical output can be produced by lifters within 10 years. This would be the case even if the electrification of transportation would greatly increase electrical demands. The United States is currently served by 1,470 coal fired generators with a total generating capacity of about 336 GWe. These plants could be replaced by modular LFTRs for a cost between $1.20 to $2,00 per watt, or from $400 billion to $700 billion. Even the larger figure would be far higher than the cost of replacement with conventional nuclear, modular small conventional nuclear, or renewable generated electricity, LFTR replacement of coal fired plants would make a 1 to 1 unit replacement ratio possible.

LFTR could also replace natural gas fired units. A 1 to 1 replacement ratio would not be required, since LFTRs could produce heated salts for storage as well as direct operation of gas turbines. Heat from stored salts could be used to run generation turbines during periods of peak demand. Thus Natural gas generating facilities could be replaced by LFTRs at a ration of up to 4 to 1. According to the EIA, there are about 5440 gas power systems with a rated capacity of 450 GWe. Let us assume that each replacement is a 125 GW LFTR, coupled with 3 extra 125 GW turbine generating systems coupled to heated salts. assume a cost of $50 million for each 125 MW turbine + salt storage system. That would give us between S300 million to $400 million per 500 MW of peak generating capacity or from $0.60 to $0.80 per Watt. Such a price would make the LFTR + salt storage system an economical replacement for natural gas. Thus the LFTR replacement for natural gas generating capacity could run as low as $270 billion for 100% replacement, with $360 billion representing the high cost.

Thus we arrive at an estimate of from 0.670 to 1.1 trillion dollars for LFTR replacement of 100% of US fossil fuel generating capacity. While this might seem like quite a lot of money, It actually represents a far lower sum than the cost of conventional nuclear or renewable generated electricity.

LFTR's can be used to produce industrial process heat, both directly or through the production of Hydrogen gas. When recombined with Oxygen, Hydrogen burns at 3200°C. or 5792°F. This should be hot enough for most industrial purposes.

Now here is where it gets interesting Suppose we build 225 GWt worth of LFTR capacity to provide direct process heat, and another 225 GWt for Hydrogen production. Now assume that 15% of the gross heat output can be recovered from industrial heating use as co-generated electricity. This would give us something around 67 GWe of extra electricity, and we can use that electricity to run the surface rail transport system, with enough electricity left over to more than cover daytime auto and truck demands for charging electricity. At night, most of the industrial process heating reactor system can be turned over to electrical generation capacity to cover 100% of transportation night storage electrical demands. The total cost of the system that will provide the industrial process heat and the electricity for transportation electrification. might reach $400 billion. There would be, by the way a tremendous savings in this arrangement. If we assume an arbitrary figure of $360 Billion per year for imported oil, and the saving of half of that figure through transportation electrification, the crude oil savings from the LFTR generation of electricity would pay for the reactors in 3 years or less, but this is not the only major economy. The savings in fuel oil and natural gas cost by transferring to the LFTRs the production of industrial heat would also produce a very large fuel savings.

So for about $1,5 trillion we get a LFTR system that provides industrial heat, electricity for nearly 100% of surface transportation and replaces all all fossil fuels in electrical generation. We get considerable savings from this deal. We save the cost of at least 80% fossil fuels that are currently burned in American society. That fuel savings would rapidly pay for the system conversion, and then once capital costs are paid for, energy costs could be dramatically lowered, to under $0.03 per kWh.

We note that the reference system mar in fact be built with over capacity, and large redundancies. Although LFTR flexibilities were expected it was not realized before the analysis that the same LFTR could booth provide industrial heat and generated the electricity to power the surface transportation system. A more comprehensive analysis might well give birth to a significantly smaller system The introduction of the factory built LFTR would seem

The low cost of LFTR generated electricity and heat would assure the competitiveness of American Industries with those of China and India, thus assuring American prosperity for a long time to come.

Over all the results of this analysis proved much better than expected. In fact the results embarrassingly good. I am afraid than my analysis will be rejected out of hand because it is so good to be believable. The whole LFTR energy system would pay for itself in less that 10 years out of fuel savings. CO2 emissions would be dramatically lowered. The cost of energy driven - process heat and electrical driven - industrial production will be lowered. The cost of transportation will be lowered. The United States will experience an Industrial Rebirth. You see what I mean about sounding too good to be true.

Fortunately I cannot promise that dogs and cats will stop fighting, that children will always obey their parents, or that Arabs and Jews will come to an agreement, or that Sylvester Stalone will ever carry a movie on the basis of acting talent.

Monday, May 25, 2009

The IFR, The LCFR and the the LFTR

Barry Brook at BraveNewClimate.com is beating the drums for the Integral Fast Reactor (IFR). I am ambivalent for a number of reasons, and will at least point to some. The IFR is not the only potential fast neutron reactor, and one fast neutron concept, the Liquid Chloride Fast Reactor belongs to the Molten Salt Reactor class. The LCFR offers significant safety, fuel processing and other technological advantages over the IFR, even though it has never been the subject of a serious R&D effort.

I represent the old ORNL tradition about nuclear technology. Oak Ridge scientists quickly rejected the idea of a sodium cooled reactor (1947 to 1950). Indeed Eugene Wigner who was the first post War research director at ORNL and who held the original patent on the Liquid Sodium Cooled Reactor, did not like his own invention. The original Oak Ridge air craft reactor was sodium cooled, but it was developed at K-25 rather than ORNL and the K-25 engineers who were developing the K-25 reactor project, quickly realized that the sodium cooled air craft reactor design had deep safety flaws including a positive coefficient of reactivity, and of course the insidious dangers of a liquid sodium coolant. Ed Bettis and his associates quickly bailed out on the liquid sodium cooled reactor design, and developed the Molten Salt Reactor concept. it was not by accident that the original K-25 MSR concept featured liquid fluoride salts, If K-25 chemists and engineers knew anything, they knew fluoride chemistry. Fluoride salts are, of course, quite safe compared to liquid sodium. The original MSR concept featured a negative coefficient of reactivity. Indeed if American Reactor development policy had been guided by strictly rational considerations from 1950 onward there would have been no more money spent on liquid sodium cooled reactors. As it is over 20 billion 2009 dollars has been spent on Sodium cooled fast breeder research without the development of a single American commercial Fast Breeder prototype.

By the early 1950's my father, C.J. Barton, Sr., was exploring the chemistry for a Liquid Chloride Fast Breeder that would have been safer, and far more practical than any LMFBR design concept. Had the LCFR rather than the LMFBR been chosen as the major direction for United States Breeder fast breeder research, and been supported at the level that the Liquid Sodium Fast Breeder was to receive, I have little doubt that an American Fast Breeder Reactor would have been developed during the 1960's. Unfortunately that was not the case, and instead over 20 billion 2009 US dollars were tossed by the United States Government down a rat hole marked Liquid Sodium Fast Breeder Reactors.

In addition to ORNL studies of the LCFR concept, a 1974 British study reached favorable conclusions about the LCFR concept, and a 1978 Swiss report indicated that the LCFB was a promising design.

In his 1982 UCLA dissertation by E. H. Ottewitte, who had participated in the Swiss study stated:
Molten salts compete favorably with liquid metals: they exhibit thermal conductivities intermediate to water and the poorer of the liquid-metal. Their specific heat capacities parallel water's. Furthermore, an intermediate coolant of molten salt should more closely match the primary salt in physical proper-
ties, thereby reducing freezing and thermal stress problems. They will cost far less then liquid metals.
Ottewitte concluded
Fast molten chloride reactors have been cursorily considered before but mainly for the U/Pu fuel cycle. The ORNL MSR program showed the feasibility of fuel salt circulation. The combination of that experience and MCFR research (out-of-pile experiments and theoretical studies, so far) provide a basis for believing the
concept will work.

Chemical stability and corrosion of molten salts are fairly predictable. Low vapor pressure of the salts enhances safety and permits low pressure structural components.

Molten fuel state and cooling out-of-core simplify component design in a radiation environment. They forego complicated refueling mechanism, close tolerances associated with solid fuel, and mechanical control devices. Molten state and low vapor pressure of the salts also offer inherent safety advantages.
In 1992 Ottewitte listed some of the advantages of the LCFR:
Some salient advantages of the MCFR concept are :
1. Simplicity : no control rods, fuel handling mechanisms, fuel elements or associated structures . Very uncluttered: should maximize test space and facilitate access thereto . Fluid fuel can be transferred remotely by pumping through pipes connecting storage and reactor .
2. MSRs don't refuel or reprocess, just add fuel and process out wastes . Continuous
processing and refueling would minimize reactor downtime . Can usefully consume all fuel forms, simplifying fuel supply while simultaneously solving other people's
problems.
3. MSR is the safest concept of all due to very strong negative temperature coefficient. No gaseous hydrogen can possibly evolve from fuel or primary coolant . Fuel already molten and handled by system . Simple design technique makes boiling impossible. Continuous removal of fission products reduces their heat source by two orders of magnitude: consequently, natural circulation suffices for emergency cooling, thereby greatly reducing the designated evacuation area . Also, under any off-normal conditions, the liquid fuel can be channeled to a continuously cooled drain tank, in a short time.
4. Very fast neutron spectrum in an annular core engenders high neutron fluxes, driving inner and outer thermal neutron flux traps, each variable in size and neutron energy spectrum by means of molten salt composition. Elimination of fuel cladding and structural material significantly improves the neutron economy of the reactor: more neutrons are available for applications.
5 .Elimination of pressurized and pressure-evolving components inside the containment, reducing risk of containment failure.
The American energy establishment, never looked seriously at the LCFR as a viable alternative to the liquid sodium fast breeder. If it had there is a likelihood that the LCFR would fave compared favorably to all LMFBR concepts including the IFR. The question would have been if a fast breeder reactor was needed at all. The LFTR offers sustainable breeding with the advantage of operating in the thermal/epithermal neutron range. The availability of a slow neutron breeding process potentially offers an enormous scalability advantage. A limited nuclear fuel supply would pose a far more serious challenge to the scalability of the IFR or a LCFR than it would to a two fluid LFTR with or without graphite.

IFR concepts during the 1990's included the notion of factory constructed modular reactors. But no assessment has been yet offered on possible interaction between IFR size and safety. Safety is a far more critical issue for the IFR than for a MSR for obvious reasons. The NRC has not yet developed safety concepts for either the LFTR or the IFR, but given the implications of major safety problems such as a coolant leak or a core rupture, IFR safety requirements are likely to be far more stringent, and costly to meet. NRC safety requirements will probably include the sort of massive safety related site construction requirements that favor economies of scale.

Compared to both the LFTR and its chloride salt cousin the LCFR, the IFR would pose significant safety hazards, and would be larger and probably more expensive to build in a factory setting. It would also pose significantly more control issues, and a system of defense in depth against sodium related safety concerns is likely to add to reactor complexity and cost. The IFR would require over 10 times as much fissionable materials as a graphite moderated LFTR making the LFTR a far more attractive candidate for the role as a mass produced, widely deployed global warming fighting technology. Indeed, factor produced small LFTRs may offer significant cost advantages over all other post-carbon energy technologies.

Politicians and scientists often feed each other's insecurities. Since the 1972 firing of Alvin Weinberg for political reasons that included his MSR advocacy and criticism of the safety of LMFBRs the American scientific community has been cowed by the orthodox dogmas of the US Department of Energy. The US government did supply limited support to the concept of a thorium fuel cycle thermal molten salt breeder from the 1950's to 1970's, and although that reactor concept received no more than 4% of the money wasted is such a profligate fashion by on the liquid sodium breeder reactor concept, that project proceed in an outstandingly successful fashion, and would have become the crowning success of the United States nuclear program if Washington had been willing to back it with even 25% of the money it wasted on the LMFBR concept.

Tuesday, April 28, 2009

LFTR Development and manufacturing costs

I was working on the question of LFTR costs. I had intended to review two documents:

ORNL-4812: Development Status of Molten-Salt Breeder Reactors
and
ORNL-5018: Program Plan for the Development of Molten-Salt Breeder Reactors

Those two documents offer a perspective on the cost of MSR developmental.

According to ORNL-4812, up to 1972 ORNL had spent $130 million dollars on MSR development. In 2009 terms this was less than than one billion dollars,

In 1980 the ORNL staff estimated that a commercial DMSR could be developed for $700 million (about 2.5 billion in 2009 dollars). Given another 2.5 billion for the development of the LFTR prototype we would have a total investment of between 5 and 6 Billion 2009 dollars investment. At that point there would be a product ready to go on the assembly line. Thus the total investment in the LFTR would be comparable to the Federal investment into the LWR. It would be one fourth the investment in so far unsuccessful LMFBR technology.

My analysis suggests that with factory production and by recycling coal fired power plants, modular LFTRs can come online for an investment as small as a dollar a watt. Let us assume that the actual cost is twice that. We still have a price for LFTRs that is lower than the 2009 price for windmills. even with a capacity factor no better than the windmills, the LFTR would be a fae better buy because of its superior flexibility.

It would be nice to imagine a private enter[rice investing in the LFTR. Is it possible? $5 billion would not be unreasonable for a private business invest in LFTR development. Consider the €11 billion plus that Airbus invested in the development of the A380. At a cost of $327 million the A380 would be if anything more expensive than the modular LFTR. In fact it is doubtful that Airbus will ever recover the Airbus 380 development cost, while the LFTR potentially could be quite profitable.

Further comparisons of the LFTR and the Airbus 380 might be in order. I suspect that the 380 would be far more complex, require far more labor input, require more exotic materials in its construction, require far more instrumentation and control, and take longer to build.

Such speculation should receive far more investigation than I have conducted, should be the subject of much more rigorous testing, and proof. I off these initial conjectures, in the hope that they will receive more investigation.

Tuesday, April 14, 2009

The Road Not Taken

The idea of a fluid fueled thorium breeder was first proposed by Nobel Laureate Eugene Wigner, together with Wigner's protégé Alvin Weinberg, and highly regarded engineer Gale Young in 1945. Between 1945 and 1958 Wigner and Weinberg who rose to be director of Oak Ridge National Laboratory had focused on a heavy water fluid fuel reactor the aqueous homogeneous reactor. But in 1948, an young Oak Ridge engineer, Ed Bettis, invented a second type of fluid fueled reactor, the Molten Salt Reactor, which was to demonstrate far greater potential as a thorium breeder and power production reactor.

Between 1950 and 1976 Oak Ridge National Laboratory developed the revolutionary Molten Salt Reactor concept. R. C. Briant and Alvin Weinberg explained in 1958 that there were
Two very different schools of reactor design have emerged since the first reactors were built. One approach, exemplified by solid fuel reactors, holds that a reactor is basically a mechanical plant; the ultimate rationalization is to be sought in simplifying the heat transfer machinery. The other approach, exemplified by liquid fuel reactors, holds that a reactor is basically a chemical plant; the ultimate rationalization is to be sought in simplifying the handling and reprocessing of fuel.
Briant and Weinberg added:
At the Oak Ridge National Laboratory we have chosen to explore the second approach to reactor development. . . . it has long been recognized that a liquid fuel which did not require high pressure, in which thorium or its compounds could dissolve, and which did not decompose under radiation would indeed be a major invention for the reactor art. . . .

we have been investigating another class of fluids which satisfies all three of the requirements for a desirable fluid fuel: large range of uranium and thorium solubility, low pressure, and no radiolytic gas production. These fluids, first suggested by R. C. Briant, are molten mixtures of UF4 and ThF4 with fluorides of the alkali metals, . . .
Scientists have pointed to the ability of the MSR to not only largely eliminate the problem of nuclear waste from its on spent fuel, but to make the nuclear waste of other reactors, largely harmless. In addition the use of MSRs to destroyed plutonium extracted from dismantled nuclear weapons has been proposed by scientists in Russia and the United States.

The Molten Salt Reactor was developed

During the 1960's, scientists and engineers built and tested an experimental Molten Salt Reactor that served as a proof of concept. They also worked on the design and development of a 1000 MWe MSR, and more briefly on a 250 MWe MSR design. At that time the estimated cost of a MSR was roughly equal to the cost of a light water reactor. Beginning about 1970 the cost of Light water reactors began a dramatic price rise that far exceeded the rate of inflation. Among the factors driving the price increase were increases in reactor size and complexity, as well as added safety features. The design of the MSR actually shifted toward greater simplicity in the late 1960's and remained relatively fixed in the 1970's. The safety issues that plagued the Light Water Reactor in the 1970's were not problems with the MSR, because many of the LWR safety problems were simply not present in the MSR design. Although an AEC document WASH-1222 complained that the MSR was a less mature technology than either the Light Water Reactor or the Liquid Metal Fast Breeder Reactor. In fact the LWR suffered from such serious design instabilities that last minute design alterations cost LWR purchasers tens of billions of dollars. Oak Ridge MSR designers reported that highly detailed $700 million development program - $2.4 Billion in 2009 dollars - would produce a viable commercial reactor - while the supposedly mature Liquid Metal Fast Breeder Reactor ended up costing over the United States government over $20 billion in 2009 dollars without ever producing a viable commercial prototype.

Thus in 2009 the 1970's to 1980's 1 GWe MSR would have cost about half the current cost of LWRs, while offering superior technology, and decreased operating expenses. The MSR would have cost less, because it was simpler, required less materials and fewer labor hours to build. The MSR had many inherent safety features that were absent from LWRs. Thus money does not have to be spent compensating for inherent safety defects in MSR design.

In addition to the savings from shifting from LWRs to MSRs, shifting from large reactors, to small, modular, factory built reactors offered an opportunity for significant construction savings. Researchers found that work disorganization was a significant cause of conventional reactor costs. Over 25 percent of workers time in reactor construction projects was wasted by work disorganization. Shifting labor from a construction site to a factory would help to solve the work flow problem. in addition building a large numbers of of small reactors in a factory, increases the rational for the use of labor savings devices on assembly lines. A rapid construction cycle, means less money would be spent on accrued interest. The small rapidly manufactured, low cost MSR is called a LFTR, Liquid Fluoride Thorium Reactor, In addition to the cost saving options already mentioned, other options are possible. It is at least conceivable that LFTR costs as low as 1 Billion Dollars per GW are possible. This is a very preliminary conclusion, but I believe that much more research should be undertaken. However, It is safe to say that some tentative evidence suggests that LFTR capital costs may run as low as $1 billion per GW, and that is a fair likelihood that LFTR costs will run below $2 Billion per GWe. Furthermore, LFTR research that would be preliminary to building pre-production prototype could run as low as $2.4 billion, and we could say that $5 billion is a not unreasonable estimate of the required research investment. Again further research would be desirable and would probably add to our certainty about cost estimates.

Sunday, April 12, 2009

LFTR Cost may run as low as 1 Billion per GWe of generating capacity

Yesterday I argued that a klawed 1970s computer model for Light Water Reactor costs had mislead the ORNL staff members who fail to see the competitive cost advantage of MSR technology over LWR technology. I argued that the technological advantage of the MSR still held. ORNL-TM-7207 assumed that the cost relationship between MSRs and LWRs assumed by ORNL-4541 (1971) was still valid, but the estimated cost of LWRs offered by ORNL-TM-7207 is far lower than what was actually the case in the index year of 1978. ORNL-TM-7207 stated that its cost estimates were based on computer modeling of reactor costs, rather than actual construction costs. However, it retrospective it is obvious that computer models of 1970's reactor costs used by ORNL was seriously flawed, and failed to capture reactor price increases between 1970 and 1980. The MSR design indexed for the DMSR was based on the the 1970 MSBR, and unlike LWRs had not undergone significant evolution. Such was not the case for the LWRs of the 1970's. And indeed in 1980 when ORNL-TM-7207 was published, the design of LWRs was continuing to evolve as the result of the Three Mile Island accident.

Thus the comparable price of LWRs and MSBRs ca. 1970 could not and should not be assumed for 1978 and even less so for the post Three Mile Island environment. The reason for this lack of evolution in MSR design can nor be fully explained by a lack of MSR design research. At least one major MSR design study emerged after the publication of ORNL-4541. But it should be noted that the MABR design had been relatively fixed at ORNL during the 1970's. There were obvious reasons why this was the case. Compared to the LWRs of 1970, 1978 or for that matter 2009, the MSBR arguably represented a significantly better form of nuclear technology. The evolution of the LWR since 1970 represents an unsatisfactory attempt to bring the LWR up with the potential of the MSBR. The MSBR was under no pressure to evolve, because it set a mark which the LWR could not equal at any price.

I believe that the case I make about the post 1978 relationship between MSBR and LWR costs requires more proof. As I noted the cost relationship between the two, set out in ORNL-TM-7207, is based on a data set found in ORNL-4541. An alternative approach to verifying the cost relationship I suggested yesterday, would be to reprice the ORNL-4541 cost estimates by determining 2009 prices. This would be a serious project, and would require much more that my once over lightly approach, but it would yield a far more definitive estimate of 2009 LFTR costs.

I believe that it is this cost advantage that lies at the heart of the case for a LFTR based energy future, I believe that this argument can and should be subjected to further tests. In particular fairly detailed design studies of two and one fluid MSR designs published by ORNL in 1979 and 71 contained fairly detailed cost information.

Until 1967 ORNL had envisioned a two fluid commercial MSR design. However, that year ORNL Reactor chemist discovered the Bismuth Protactinium recovery process which allowed thorium breeding in a single fluid core reactor. The single core reactor approach was considered advantageous By ORNL because it eased core graphite problems. The improvement in graphite performance was considered desirable enough to justify a switch from a one fluid 1 GWe commercial design.

ORNL MSBR had considered the possibility of both 1 GWe and 250 MWe modular two fluid designs. Both contain data that is relevant to LFTR costs. ORNL-4528 is especially interesting because it describes a facility powered by 4 250 MWe MSRs. In addition we have the 1962 Sargent & Lundy Report CAPITAL COST EVALUATION, 1000 MWe MOLTEN SALT CONVERTER REACTOR POWER PLANTS. This study was prepared under contract from ORNL. Unfortunately the Sargent & Lundy report was the most detailed, and it was perpared when thinking about large MSR power generation projects was thew least evolved. I am pointing these studies out because they serve as good starting points for determining LFTR costs.

Sargent & Lundy estimated the construction cost of the MSR to have been $65,481,000 1962 dollars, say 460 million 2009. No one who knows about power generation capitol cost would take that figure seriously. ORNL-3996 suggested 103 million in direct construct costs and another 30 million in indirect costs, and $110 million in interest, all in 1966 dollars. ORNL-3996 appears to have attempted to find a more realistic picture of commercial MSR costs., and we get a total cost of $243 Million 1966 dollars, or 1.6 billion 2009 dollars.

ORNL-4528 estimated facility costs to run to $146 million, about the equivalent estimate for a 1 GWe LWR facility was estimated to cost in 1967. ORNL-4541 estimated capitol costs for a 1 GWe MSR was 202 Million 1970 dollars, including 30 million accumulated interest during construction. Assuming another 200 million in interest we get a total price tag of 400 million to tax payers. That translates to 2.64 billion 2009 dollars. I take note of the fact that my Thursday calculation of MSR cost were off by a billion dollars or so, no doubt because the DMSR study did not include the cost of interest in their calculations. So we have a little reason for confidence in our ORNL-4541 cost estimate. There is also egg on my face as a consequence of my little calculation error of Thursday. I don't suppose you would believe me if i said that it was the first time I had ever made a mistake? The second time? Oh well.

ORNL-4528 looks like it calculated contingencies too low, way too low probably and underestimated interest accumulated during construction. That gets us a figure that is about 10% less that the ORNL-4541 cost estimate. There are other ample opportunities for fudging on the 1967 cost estimate, thus ORNL-4528 and ORNL-4541 are assuming the same universe of capital costs. This is not terrribly shocking since Roy C. Robertsons name went on the front cover of ORNL-3996, ORNL-4528, and ORNL-4541, and Ed Bettis's name went on the front cover of the first two.

I realize that I am pushing my analysis to a level of obtuseness that has long sent me readers packing, but there is a point here, and one that would make a nice master's thesis for a nuclear engineering student. That point is that in the 1962 to 1970 ORNL cost estimates for MSR power plants were not just off the top of the head guesses, and thus would be serious starting points for for attempts to better determine LFTR costs.

Lets go back to the 2.64 billion calculation, the inflation adjusted costs of the 1970 ORNL-4541 cost estimate. Let us assume that factor production decreases overall cost by 20% and that the rapid manufacture decreases accumulated interest by 2/3rds. Further let us assume that by recycling old power plant sites we are able to save 5% on capital costs. Finally assume a 30% cost savings due to the learning curve enjoyed by serial manufacturing of hundreds of LFTRs. That brings our capitol costs down to the neighborhood of 1.2 Billion dollars. This is lmost too good to be true, and needs more work,

I do see my goal, however. Lets see what we can reasonably say. First that ORNL made a realistic study of commercial MSR and noted that MSR costs at that time would have been similar to LWR costs. That during the 1970;s LWRs underwent design changes that made them more expensive, but there was no similar design change for the MSR. That given inflation in 2009 the cost of MSRs would probably run about half what LWRs cost if the LFTRs were built in the same way LWRs are built. However factory built LFTRs would cost significantly less than custom built MSRs because of the labor cost advantage of factory manufacture, the decrease of accumulated interest because ofrapid manufacture, the cost savings of recycling old power plants and the finally the learning related cost savings related to serial manufacture. Taken all together, we have a potential power generating product that appears may cost less than 2 Billion dollars per GWe of generation capacity, and it is not impossible that factory built LFTRs might cost as little as one billion dollars per GW of generating capacity.

There is a well documented data set derived from research don at ORNL in the 1960's. Further research using the ORNL data set and recent materials and manufacturing cost data, might refine the potential LFTR cost picture.

I intend to clean up my analysis, and make it a little easier to read, and present the repackaged text very soon.

Thursday, April 9, 2009

On the Cost of LFTRs: ORNL-TM-7207 and Moir

I looked once again at Ralph Moir's study on MSR costs, and I realized that Moir's data set came from ORNL-TM-7207, a document describing a Denatured MSR using U-238 as a proliferation resistance tool. ORNL-TM-7207 contained a fairly detailed design study that was in turn based on ORNL MSBR research of the late 1960's and early 70's. The information of MSR costs was really derive from cost studies for the MSBR. ORNL cost estimates for the MSBR had been updated as recently as 1975. So
[u]sing a construction materials and labor increase of P2%/year gives a multiplier of 1.4 and a cost for the MSTR in 1978 of about $680 million.

A detailed estimate of the cost of a 1000-MWe DMSR based on a mature technology is given in it fol%owing seetion, From this, we have estimated the cost of a first standardized DMSR by applying a factor of 1.5 to allow for increased first-of-a-kind costs and the cost of a lead commercial prototype by applying another factor of 1.5 to allow for increased prototype costs, Using this proceduree the cost of a POOO-Mk prototype DMSR is estimated to be $1470 million and the first standardized DMSR $980 million
Note that at ORNL in 1980 the MSR was regarded as"a mature technology".
Since MSR research and development has been under way for some 30 years, the basic technology is well understood. However, much of it has not been developed to the stage and scale that would be required for the construction of large reactor systems, Thus, a significant R&D effort would be an important part of any program to commercialize MSRs, In addition, untfl recently, development was concentrated on reactor concepts with a good breeding gain and a low fissile inventory sO that the resulting thermal breeder reactor system would have a reasonably short doubling time and could be considered a viable alternative (or complement) to fast breeder systems. The technology needs of the modified reactor concept that has been developed in response to the recent emphasis on proliferation resistance differ from those of the nominal breeder concept.
In short many of the ORNL concerns under consideration for the 1980 concept might be rethought today. Some might well be discarded, while others might well have already found partial or even complete solutions through other lines of research.

Thus a further R&D program would be needed to bring a commercial MSR online. They projected a business as usual program which included the building and testing of a 200 MWe to 250 MWe Developmental prototype.
The complete base program is projected to cost about $700 million [2.37 billion 2009 US dollars] over about 30 years.
It should be further noted that the pace of development would have been slow, as was the case for MSBR Development at ORNL after the MSRE was shut down in 1969, Thus we have a cost estimates based on business as usual assumptions.
The construction cost of the MSTR way be estimated by updating the cost estimate for the MSTR prepared in 1975 for the MSBR program. Using a construction materials and labor increase of P2%/year gives a multiplier of 1.4 and a cost for the MSTR in 1978 of about $680 million.

A detailed estimate of the cost of a l000-MWe DMSR based on a mature technology is given in it fol%owing seetion, From this, we have estimated the cost of a first standardized DMSR by applying a factor of 1.5 to allow for increased first-of-a-kind costs and the cost of a lead construction prototype by applying another factor of 1.5 to allow for increased prototype costs, Using this proceduree the cost of a 1000-MW prototype DMSR is estimated to be $1470 miliom and the first standardized DMSR $980 million.
The ORNL staff found that:
The DMSR is estimated to cost $653 million, or about .$650/kWe in 1978
dollars.
But the 1975 cost estimates were based on 1970 MSBR cost estimates:
costs were taken (for most accounts) as the basis for the DMSR estimate using the following method.
1. The costs were adjusted to take into account the differences in size or other requirements for the DMSR. For example, the reactor vessel cost was increased to take into account the larger size of the DMSR vessel.

2. The 1978 costs were increased by a multiplier based on the increase in construction materials and labor costs from 1970 to 1978. 'The multiplier was calculated to be in the range 2.3 to 2.5; to be conservative, the multiplier 2.5 was used. This represents an annual rate of increase of about 12X,

In addition, the costs of a pressurized-water reactor (PWR), a bailing-water reactor (BUR), and a coal-fired plant in 1978 were estimated usimg the CONCEPT V code. Were appropriate, some accounts were estimated based the analogous account in one of the CONCEPT estimates. For example, the turbine-generator cost was based on the coal-fired plant estimate because the same type of supercritical steam turbine would be used.
So we have a good idea of the methods which the ORNL staff used to come up with their 1980 DMSR estimate. Further it would appear that the original 1970 cost estimate was to a great extent based on interpolation of coal an LWR power plants ca. 1970. But something is wrong with the model. we are told that in 1978 nuclear capital costs ran
$600/kWe for a PWR plant and $38O/kWe for a coal plant without flue-gas cleaning.
in fact in 1978 PWRs cost a great deal more than the ORNL estimate. A Harvard-M.I.T. study conducted in the mid 1970's found that nuclear capital costs had increased two to three times faster than coal capital costs between the late 1960s and mid-1970s. That trend continued into the 1980's and by the end of the decade nuclear capital costs ran 2.5 times that of coal. In addition to capital cost increases in terms of constant dsollars, inflation increased capital cost for all energy sources. Thus the sort of LWR cost estimates offered by the ORNL staff in ORNL-TM-7207 were extremely inaccurate.

Were the capital costs for the DMSR equally inaccurate? This would not appear to be the case. First while LWR design had undergone substantial and rapid modification between 1970 and 1980,. These design changes, more than any other factor, were responsible for the dramatic increase LWR costs. In contrast, MSR design was basically unchanged form 1970 to 1980. There were of course many design variants, but they had been explored by 1970. This design stability that is characteristic of a mature reactor concept. It is unlikely then that the real cost of MSR would have tracked the price change of LWRs. The cost of LWRs increased by 700% between 1970 and 1980. Once inflationary changes are factored out, LWR capital costs were about 2.8 times higher in 1980 than they were in 1970. Thus while the ORNL staff estimated the cost of a conventional nuclear reactor to be $600 million in 1978, it was probably closer to $1.5 billion. Thus while the ORNL staff would have expected the DMSR to cost $653 million in contrast to the LWR's $597 Million, in fact the LWR probably would have cost closer to $1.5 billion, giving us a DMSR cost of 43% of the LWR. Hay wait a minute, could this be possible? Well if the arguments I have been making regarding LFTR costs is valid, yes it is. In fact, this figure does not take into account many potential LFTR cost savings that were not considered by the ORNL staff in 1980. For example, research has shown that about 27% of worker's time was wasted because of worj flow disorganization at reactor construction sites.

Factory built LFTRs could expect to see workers' time used more efficiently. And of course LFTR factories could install labor saving devices. I have noted siting innovations, including underground siting. The rapid manufacture and set up of small factory built LFTRs would also decrease interest costs. The rapid manufacture of large numbers of small LFTRs would introduce the cost saving avaliable to serial production. The Chinese expect the learning curve for small factory built reactors will yield a 30% cost savings. Rapid manufacture and set up greatly decreases accrued interest. The small LFTR appears to offer a perfect storm of cost savings,

Thus there is probable cause to believe that LFTR capital costs will be 1/4th of that of conventional nuclear or less.

Wednesday, April 1, 2009

The cost savings potential of LFTR technology

In a previous essay, I noted that to areas on which nuclear cost lowering efforts could be focused. These include reactor complexity and labor costs. I suggested that generation IV technology reactor held promise for cost lowering in both areas, but found that Chinese Pebble Bed Reactors did not offer significant cost benefits when compared to the Chinese Light Water Reactors.

I wish to focus in this essay on the cost lowering potential of another Generation IV Reactor the Thorium Molten Salt Reactor or as it is also called the Liquid Fluoride Thorium Reactor.

I have chose to look closely at the LFTR because it is arguably the most promising of all nuclear technologies in terms of scalability, rapid deployment, safety, nuclear waste management, "green" qualities, and sustainability. The LFTR has outstanding safety features. It can convert thorium into nuclear fuel with 98% efficiency. The thorium fuel cycle is much cleaner that the uranium fuel cycle in terms of undesirable nuclear byproducts, and long term radiation dangers. In the LFTR, thorium produces about 0.1% of the volume of long term nuclear waste produced by the Light Water Reactor The LFTR designers can take advantage of the laws of nature to give the LFTR very desirable safety features. Fuel can be removed and replaced in the LFTR without interrupting its operations. The LFTR extremely scalable. LFTRs can be designed and built to produce anywhere between 5 MWe and 5 GWe. LFTRs offer the possibility of manufacturer in large number over a short period of time. LFTRs design can conform to the principles of green engineering without compromising efficiency. LFTR thorium based fuel supply is sustainable with enough thorium to provide energy for millions of years potentially available.

During the 1940's Nobel Prize wining physicist Eugene Wigner identified thorium fueled liquid core reactors as offering the greatest potential for low cost long term replacement of coal as an ebergy source. An Oak Ridge chemist Raymond C. Bryant first noted that the the Molten Salt Reactor had excellent potential as a thorium cycle reactor. The Molten Salt reactor was invented by an Oak Ridge engineer Ed Bettis in in 1948 and underwent extensive research and development in Oak Ridge between 1950 and 1976.

Two MSR prototypes were built in Oak Ridge, and the design of an electricity producing advanced thorium fuel cycle MSR was underway in Oak Ridge, when Washington ordered the termination of MSR research Nixon era AEC political infighting and budget cuts were behind the decision, but Oak Ridge scientists remained convinced of the LFTRs unique promise.

I am familiar with the MSR because my father, C.J. Barton, Sr., was involved in a great deal of the pioneering chemistry research on what is often called the chemist's reactor.

There are several potential variations of the MSR/LFTR design. All are far simpler than the LWRs. All are far lighter and far more compact. Because of its simplicity, light weight, and compact design, LFTRs that can produce useful amount of power can be manufactured on factory assembly lines and transported by truck, rail or barge to power plant locations where they can be rapidly put into operation.

The potential for labor saving with the LFTR design is very significant. Light water reactor require between 10 million and 20 million hours of labor to manufacture. Through use of labor saving technology and the potential for LFTR design simplicity is is conceivable that LFTRs can be produced with no more than 10% of the labor input of LWRs. The LFTR has the potential to create a revolutionary breakthrough in energy prices and would allow the United States to produce electricity at a cost that would be competitive with electricity produced by low cost Chinese and Indian Reactors.

Tuesday, March 24, 2009

The Big Lots Reactor Discussions

There has been some discussion of my Big Lots Reactor concept in the Energy from Thorium discussion pages. It would appear from comments that I needed to make things clearer. I offered some clarifications of my Big Lots reactor concept.

There are a number of significant issues in LFTR Design. The two most important issues are the graphite moderator issue, and the one or two fluids issue. The graphite moderator issue has to do with neutron energy in the reactor core. There are two major moderators that are commonly used in reactors, heavy water and graphite. Although there have been proposals to use heavy water as a moderator in LFTRs, to do so would introduce a complication in core design that would lead inevitably to higher R&D expenses. My view is that early LFTR design should go with options that require less research when ever possible. That would suggest then that graphite would be the moderator of choice, even though graphite carries some liabilities.

There is a school of thought that holds that the best solution to the moderator problem is to have none. I might find this approach valid if were were going to be dealing with a limited number of reactors. We are not. I calculated the number of 100 MW "Big Lots" Reactors that would be needed to replace fossil fuel powered electrical generators in the United States. My estimate would be in the neighborhood of 10,000. Using a graphite moderated core design means that only about a fifth as much fissionable materials will be needed to start a moderated LFTR as are needed to start an unmoderated LFTR. The problem is one of scalability. We can start 5 times as many graphite moderated LFTRs with a given amount of fissionable material as we can start if the LFTRs are unmoderated.

Thus a graphite moderated LFTR makes large scale LFTR deployment more easy to manage. This decision is not a difficult one to make.

The second major design decision is between two and one fluid core designs. In a two fluid core design the thorium carrying is segregated from the uranium carrying salt. As thorium-232 absorbs neutrons, it almost always goes through a 2 stage transformational process that produces fissionable U-233. On the first stage Th-233 emits an electron and becomes protactinium-233. Pa-233 then emits an electron and becomes U-233. In a one fluid Th-232, Pa-233 and U-233 would all be in a single fluid. There is a problem with this because Pa-233 is a neutron eater, and that does two bad things. First every Pa-233 atom that absorbs a core neutron is one less U-233 atom that will be produced by the LFTR breeding process. Secondly every neutron that is absorbed by Pa-233, is one less neutron that is available to breed Th-232 into U-233. So every time Pa-233 absorbs a neutron, two U-233 atoms are lost to the breeding process.

The obvious solution to this little problem is to process Pa-233 out of the core salts as quickly as possible. But as my father discovered in the 1960's when he tried to find how to do this, processing Pa-233 out of the core salts of a single fluid MSR is quite a challenge. The added chemical processing equipment required by a single fluid design would add to reactor cost.

In contrast, Pa-232 poses less of a problem in a two fluid core and blanket design. In a core and blanket design the core is surrounded by an outer donut that contains thorium salts, and other carrier salts. The blanket serves a double purpose. Thorium in the blanket captures the neutrons that leak from the core. Thus the blanket is a radiation shield. Because blanket thorium is not mixed with with the core salts, it can be present in the blanket at a much higher concentration that would be the case in a single fluid design. The higher concentration of Th-232 would prevent the Pa-233 neutron absorption problem from becoming significant in the blanket, because there would be many more Th-232 than Pa-233 atoms in the blanket.

Solving the Pa-233 problem is likely to involve more R&D and increase the cost of the "Big Lots" reactor.

We are of course left with problems with our design choices. The primary problem is that when energetic neutrons encounter carbon atoms in graphite they tend to knock those atoms around. This process causes graphite to swell, and makes it a poor material for core structures. It has been suggested, for example that core graphite could be present in the form of balls that float in the core salt. Periodically the graphite balls would be floated out of the core to be replaced by fresh undamaged balls. A more likely solution would be to shut a graphite cored LFTR down every few years, remove the damaged core, and replace it with a fresh core. The damaged core would be, of course, highly radioactive, and it most likely would have to go into long term storage. Graphite does not pose much of a long term storage problem, but used LFTR cores would be classified as nuclear waste. It would be highly desirable to have a low cost long term core graphite disposal plan before the "Big Lots" reactor went into production.

The "Big Lots" concept was born because I saw that the requirements of load following/peak load power generation would lead to longer graphite core life, as well as permit the use of lower cost materials like stainless steel in reactor manufacture. The use of stainless steel would require a lower reactor temperature, and the decrease in neutron exposure that a reactor that might be operated on a part time, part power basis would increase the life span of graphite and metal structural components.

It is clear that I have shamelessly advocated what might be called marketing based design process over a purely technological. Under ordinary circumstances I would not dream of second guessing the scientists and engineers, but my interest is not in building the best possible reactor but in building a reactor that is good enough and highly scalable.

Sunday, February 15, 2009

The Greatest Bargain of the 21st Century.

In May of 2008, I posted a series of posts on the cost lowering potential of LFTR technology for nuclear power. I was able to point to a number of areas in which significant cost lowering potential was present, especially in comparison with Light Water reactor costs. I did not attempt to assign a cost number but a figure of 25% of the cost of conventional nuclear power generating reactors seemed plausible. It is possible that LFTR costs might not be that low, if attention is not paid to rigorous application of the cost lowering potentials.

Why does the LFTR have such cost lowering potential?

First because its design is very simple compared to LWRs. LWRs require many hundreds of valves, miles of pipes, numerous pumps, thousands of supports, miles of cables, hundreds of embedded instruments and other parts, each built to very exacting specifications and requiring intensive highly skilled labor for their installation. Mistakes in parts installation may necessitate large scale rebuilding. Constant monitoring of the quality of reactor construction is of the utmost necessity, and consumes many hundreds of thousands of hours of supervisors time. The LWR has two active control systems. It has at least two cooling systems, and a massive 8" thick pressure vessel that surrounds the reactor. The LWR operates under high pressure conditions. Coolant water is pumped under high pressure through hundreds of channels in the reactor's core. The entire core coolant system is built to very exacting specifications. Even a minor failure of the coolant system could lead to core damage. Thus the LWR is a highly complex machine, requiring hundreds of thousands of parts and millions of hours of labor to construct. LWR construction requires great organizational skills, and extremely diligent supervision. It is relatively easy for very costly problems to emerge during the construction. For example, if cement used in the reactor construction does not conform to design specifications, structures built with inferior cement have to be torn down and rebuilt. Such problems can lead to delays in construction schedule, and significantly contribute to project cost. The construction method, which requires the use of a huge amount of on site labor , is very difficult to organize and control. Problems associated with the complex reactor construction labor system contribute to overall reactor costs.

In contrast Molten Salt Reactors including the LFTR are very simple. A liquid coolant fuel mixture is pumped through the reactor core and then through a heat exchanger and back into the reactor. There may be a secondary cooling system if the primary system breaks down, there would also be an emergency back up system that would automatically drain the core if both cooling systems failed. The core would be drained into specially designed tanks that would be passively cooled, by a naturally circulating air or water coolant system.

The LFTR reactor can be designed to include several small chemical processing units. These units greatly improve the efficiency of LFTR operations. While they add to LFTR complexity, even with a full array of chemical processing units, the LFTR is still far less complex than the LWR. One of the keys to lowering LFTR costs is the simplicity of the LFTR design.

The LFTR operates at a much higher temperature than LWRs. For that reason a small LFTR will operate with greater thermal efficiency than a very large LWR. This opens the door to greater design flexibility. With LFTRs, designers have significant design options related to size. LFTRs can be designed for modular use. Several small LFTRs can be clustered to produce the power equivalent of one large reactor. There are a number of advantages in doing so. Small reactors can be factory built, and transported by truck, train or barge to a final set up site. Factory production would use labor more efficiently, and product quality could be much more easily controlled. A serial production process would lead to rapid learning, improved quality and lower price. Reactors could be built in periods of a few months rather than several years. The significantly shorter construction time would have a positive effect on overall reactor costs:
A. The cost of accrued interest during the construction phase would be significantly less or factory built small reactors than for site-built large reactors.
B. Small reactors can be set up and brought on line within months of being ordered, thus quickly adding to the owner's revenue stream.
C. Small, low cost, quickly set up reactors have fewer risks. Lower risk premium, lower capital costs.
Small modular LFTRs allow greater flexibility in reactor siting and housing:
A. Old coal and natural gas power plant sites can be recycled with considerable economies.
B. New grid hookups would not be required. LFTRs sited at old power plant sites, could use the existing grid hookup.
C. On site facilities could be reused, decreasing construction expenses.
D. The location of small reactors close to electrical consumers would conform more closely to a distributive model, and would assure greater grid stability by bringing electrical production close to the customers. This reduces the necessity of making costly additions to the grid.
LFTRs do not require expensive, hard to obtain materials that could compromise LFTR production. In addition to materials options explored at ORNL between the 1950's and the 1970's a variety of other materials options appear to be available. These include Carbon-carbon composites which can be used with very high performance LFTRs that can produce industrial process heat, and commodity materials like stainless steel, that can be used to lower LFTR costs even further. Ultra low cost LFTRs might be used to replace natural gas fired generators that are currently used in peak reserve capacity.

The LFTR opens the door to relatively novel, innovative and low cost housing options, that can enhance reactor safety while lowering costs. Underground or underwater housing should be explored. LFTRs can be housed in underground chambers on existing power plant sites. Such chambers need not require massive amounts of steel, and concrete, as present reactor containment structures do. Underground reactors would have superior protection against terrorist attacks through car bombs or large aircraft attacks. They could easily be made relatively impervious to attempts by terrorists to seize the reactor. Finally underground reactor can be designed to include multiple anti-proliferation barriers, making the underground reactor a highly undesirable target for would be proliferating nuclear terrorists. These very desirable goals can be achieved without the high cost of above ground massive containment structures.

In addition to the use of recycled coal plants for underground sites, mines could be used for LFTR siting. Salt mines make a very interesting option, with the potential of clustering a relatively large number of modular LFTRs in salt mines, with no above ground structures required.

In addition to the many cost lowering options available to LFTR designers and operating utilities, the LFTR can be designed to operate without operational staff. Since the LFTR is highly stable under passive control, no operator input is required in order to assure the highest level of safety. Thus while security staff would be required to protect LFTRs from terrorists and misguided acts of vandalism, no operators are required for safe and efficient LFTR operation and an operational staff would be redundant. This would lead to further economies in LFTR design, construction and operation.

It is quite obvious that LFTR costs could be substantially less than Light Water Reactor costs. At the moment it is far future LWR costs that are far from clear. My own guess is that if all of the LFTR economies I have mentioned were implemented the relative cost savings of the LFTR would be greater than 50% of the cost of Light Water Reactors, and LFTRs might well cost 25% of the cost of LWRs. If we consider that large amounts of LFTR fuel has already been mined and is currently regarded as mine waste, the LFTR could well turn out to be the greatest bargain of the 21st century.

Followers

Blog Archive

Some neat videos

Nuclear Advocacy Webring
Ring Owner: Nuclear is Our Future Site: Nuclear is Our Future
Free Site Ring from Bravenet Free Site Ring from Bravenet Free Site Ring from Bravenet Free Site Ring from Bravenet Free Site Ring from Bravenet
Get Your Free Web Ring
by Bravenet.com
Dr. Joe Bonometti speaking on thorium/LFTR technology at Georgia Tech David LeBlanc on LFTR/MSR technology Robert Hargraves on AIM High